SolarAPP+ Adoption At a Glance

The permitting process was
taking four weeks. Now with
SolarAPP+ we give a permit
the same day.
-Tucson, AZ Mayor Regina Romero
Jurisdiction Adoption and Piloting
Statistics at a Glance

Currently, 27 communities are using SolarAPP+, with over 10,270 permits issued, 59,350 kilowatts approved, and 10,270 estimated hours saved in review time.

Read more in the SolarAPP+ Pilot Analysis Report.

Authority Having Jurisdiction Adoption Status Technologies Available PV Permits Issued PV + Storage Permits Issued* Total kW Approved Estimated Time Saved on 1st Permit Review (hours)**
Benicia, CA Fully Adopted PV, Piloting PV+ Storage 59 19 410 78
Dublin, CA Fully Adopted PV, Piloting PV+ Storage 43 17 27 60
Menifee, CA Fully Adopted PV, Piloting PV+ Storage 1,191 47 6,210 1,238
Modesto, CA Fully Adopted PV, Piloting PV+ Storage 191 4 1,028 195
Pima County, AZ Fully Adopted PV, Piloting PV+ Storage 2,283 100 15,380 2,383
Pleasant Hill, CA Fully Adopted PV, Piloting PV+ Storage 96 31 588 127
San Luis Obispo, CA Fully Adopted PV 10 - 46 10
San Ramon, CA Fully Adopted PV, Piloting PV+ Storage 247 124 2,218 371
Simi Valley, CA Fully Adopted PV, Piloting PV+ Storage 512 173 3,749 685
Sonoma County, CA Fully Adopted PV, Piloting PV+ Storage 97 37 803 134
Stockton, CA Fully Adopted PV, Piloting PV+ Storage 655 24 3,822 679
Tucson, AZ Fully Adopted PV, Piloting PV+ Storage 3,587 72 21,584 3,659
Beaumont, CA Piloting PV, Piloting PV+ Storage 99 16 555 115
Culpeper County, VA Piloting Piloting PV and PV+ Storage - - 0 0
Gilroy, CA Piloting Piloting PV 23 - 35 23
Guilford, CT Piloting Piloting PV and PV+ Storage - - 0 0
Harrisonburg, VA Piloting Piloting PV and PV+ Storage - - 0 0
Kern County, CA Piloting Piloting PV and PV+ Storage 2 1 16 3
Palo Alto, CA Piloting Piloting PV 5 - 24 5
Phoenix, AZ Piloting Piloting PV 341 - 2,206 341
Pinole, CA Piloting Piloting PV 14 - 10 14
Sacramento County, CA Piloting Piloting PV 16 - 86 16
San Joaquin County, CA Piloting Piloting PV and PV+ Storage 4 - 33 4
San Pablo, CA Piloting Piloting PV 2 - 8 2
Calistoga, CA Testing Testing PV 3 - 207 3
Oceanside, CA Testing Testing PV 72 - 299 72
Richmond, CA Testing Testing PV 57 - 12 57
Totals 9,609 665 59,356 10,274
Data as of 09/19/2022
*Issued via Pilot
**Estimated 1 hour saved per application
Interest in SolarAPP+
Interested Installers Engaged Jurisdictions
Across the country, installers are interested in
utilizing SolarApp+ for permit review
Cities and counties across the country have shown
their interest in adopting SolarApp+
Permit Time Savings for Adopting Jurisdiction

SolarAPP+ has reduced permit timelines from
as many as 20 business days to zero