SolarAPP+ Adoption At a Glance

The permitting process was
taking four weeks. Now with
SolarAPP+ we give a permit
the same day.
-Tucson, AZ Mayor Regina Romero
Jurisdiction Adoption and Piloting
Statistics at a Glance

Currently, 32 communities are using SolarAPP+, with over 15,000 permits issued, 100,000 kilowatts approved, and 15,000 estimated hours saved in review time.

Read more in the SolarAPP+ Pilot Analysis Report.

Authority Having Jurisdiction Adoption Status Technologies Available PV Permits Issued PV + Storage Permits Issued* Total kW Approved Estimated Time Saved on 1st Permit Review (hours)**
City of Benicia, CA Fully Adopted PV, Piloting PV+ Storage 83 21 609 104
City of Dublin, CA Fully Adopted PV, Piloting PV+ Storage 123 72 1,239 195
City of Modesto, CA Fully Adopted PV, Piloting PV+ Storage 278 19 1,858 297
City of Pleasant Hill, CA Fully Adopted PV, Piloting PV+ Storage 119 41 956 160
City of San Luis Obispo, CA Fully Adopted PV, Piloting PV+ Storage 70 15 361 85
City of San Marcos, CA Fully Adopted PV, Piloting PV+ Storage 64 4 372 68
City of San Ramon, CA Fully Adopted PV, Piloting PV+ Storage 348 168 3,495 516
City of Simi Valley, CA Fully Adopted PV, Piloting PV+ Storage 771 213 6,416 984
City of Stockton, CA Fully Adopted PV, Piloting PV+ Storage 980 41 6,284 1,021
City of Tucson, AZ Fully Adopted PV, Piloting PV+ Storage 4,371 80 29,927 4,451
County of Sacramento, CA Fully Adopted Piloting PV 109 - 586 109
County of Sonoma, CA Fully Adopted PV, Piloting PV+ Storage 142 61 1,351 203
Menifee, CA Fully Adopted PV, Piloting PV+ Storage 1,587 64 9,591 1,651
Pima County, AZ Fully Adopted PV, Piloting PV+ Storage 2,754 111 21,561 2,865
City of Alameda, CA Piloting Piloting PV and PV+ Storage 2 - 3 2
City of Beaumont, CA Piloting Piloting PV and PV+ Storage 175 33 1,244 208
City of Gilroy, CA Piloting Piloting PV 101 - 591 101
City of Houston, TX Piloting Piloting PV 178 - 1,368 178
City of Palo Alto, CA Piloting Piloting PV 14 - 81 14
City of Phoenix, AZ Piloting Piloting PV 1,249 - 8,405 1,249
City of Pinole, CA Piloting Piloting PV 19 - 96 19
City of San Pablo, CA Piloting Piloting PV 9 - 32 9
City of Tracy, CA Piloting Piloting PV 26 - 170 26
County of Kern, CA Piloting Piloting PV and PV+ Storage 2 2 31 4
Culpeper County, VA Piloting Piloting PV and PV+ Storage 17 - 145 17
El Cajon, CA Piloting Testing PV and PV+ Storage 206 6 1,155 212
Harrisonburg, VA Piloting Piloting PV and PV+ Storage 9 - 66 9
San Joaquin County, CA Piloting Piloting PV and PV+ Storage 102 17 861 119
Town of Guilford, CT Piloting Piloting PV and PV+ Storage 6 - 48 6
Calistoga, CA Testing Testing PV 5 - 23 5
City of Richmond, CA Testing Testing PV 93 - 393 93
Oceanside, CA Testing Testing PV 134 - 647 134
Totals 14,146 968 99,966 15,114
Data as of 02/10/2023
*Issued via Pilot
**Estimated 1 hour saved per application
Interest in SolarAPP+
Interested Installers Engaged Jurisdictions
Across the country, installers are interested in
utilizing SolarApp+ for permit review
Cities and counties across the country have shown
their interest in adopting SolarApp+
Permit Time Savings for Adopting Jurisdiction

SolarAPP+ has reduced permit timelines from
as many as 20 business days to zero